To-do list of Headboard
This is a to-do list of the headboard during the 2022 winter quarter.
By the end of the last quarter, the schematic and PCB layout had been completed. There are still following tasks to be finished during this quarter.
-
Finalize the type of +48V power connector on the headboard. -
Double-check the final design and modify the layout/routing if needed. -
Purchase electronic components including resistors, capacitors, resonators, USB-A/RJ45 plugs/jacks, etc. -
When the board comes back from the fab, solder the components to the board (manually or via machine). -
Plug the initial board into the USB hub and check whether the CircuitPy driver works on the PC. -
Debug if the board doesn't work.