......@@ -126,11 +126,16 @@ things do change, having thought a plan through will let you
more easily understand the implications and how you want to adapt
in response.
Recall that the last 2 weeks of the quarter will be building
a Fractal Flyer and getting it working. You're therefore making
a plan for weeks 2-8, at which point you should have completed
your project with sufficient quantity that the class can build
5 Fractal Flyers.
The last 2 weeks of the quarter will be building
complete Fractal Flyers and getting them working. We're setting
asidse two weeks because it is almost certain that your schedules
will slip a little, due to details or unforeseen challenges (e.g.,
a package containing materials is delayed a few days).
You're therefore making a plan for weeks 2-8. The wings
group may schedule workshops in weeks 9 and 10, but they
should be final workshops to finish up: the expectation
is that by the end of week 8 the building process is extremely
polished and working with high yield.
Your plan should:
......@@ -171,13 +176,15 @@ Your plan should:
can help.
Your plan should be 2-3 pages. You can use a spreadsheet to
show timelines, or figures, or tables. whatever works best for you.
show timelines, or figures, or tables. Whatever works best for you.
If you have questions or are uncertain about certain aspects of
the Flyer, do not hesitate to reach out. You can email all of us
at the staff mailing list ee185-aut2122-staff@lists.stanford.edu.
at the staff mailing list ee185-aut2122-staff@lists.stanford.edu
(since the staff is the same as autumn we're just reusing the
list).
We will share and discuss the plans in class on Wednesday.
We will share and discuss the plans in class on Monday.